Johnston's Highway 141 Interchange Has Had a Different Price Tag in Almost Every Document. Here's What the Paperwork Shows.

October 29, 2026

Drivers on Towner Drive west of Iowa 141 lost their direct connection to the highway a year ago. The Iowa DOT permanently closed the west leg of Towner Drive at Iowa 141 starting October 13, 2025, removed several median crossovers in the area, and sent traffic to NW 121st Street.

The interchange meant to replace that kind of access has a design and a preferred alternative. Its cost and schedule are another matter: depending on which public document you open, construction starts in 2027 or 2028 and wraps up as late as 2030, and the price runs from about $18 million to $36 million. For anyone buying or selling near Iowa 141 and NW Towner Drive, the access closures are on a firmer track than the interchange that replaces them. A home's route to the highway is still changing.

The closures aren't waiting for the interchange

The 2025 Towner closure was part of Iowa DOT's changes to the Iowa 141 corridor to improve safety. It didn't depend on the new interchange being built or funded. City leaders have said more of the same is coming. In a KCCI report from August 3, 2026, Mayor Paula Dierenfeld said the Iowa DOT told the city it will not allow any more at-grade intersections along the corridor, and she described what comes next:

"Over time, we're going to see those other at-grade intersections change into something that looks more like this."

The traffic numbers explain why. In a June 9, 2026 presentation to the Iowa DOT Commission, the city put Iowa 141 west of NW 121st Street at about 19,710 vehicles a day in 2023, with a forecast of about 35,200 by 2050. North of the IA 44 interchange, the 2023 count was about 32,910, forecast to reach about 61,900 by 2050. The 2050 figures assume full build-out. City leaders gave KCCI a higher figure for the highway as a whole, about 50,000 vehicles a day.

Three streets on the closure list

Engineers looked at five interchange designs: a roundabout, a skewed roundabout, a diamond, a single point urban interchange, and a folded diamond. The city's preferred choice is the skewed roundabout. According to the June presentation, it would close:

  • the existing NW Towner Drive connection
  • NW Timberridge Lane
  • NW Timberbrooke Lane

The same slide says the skew is meant to limit impacts to the golf course and to provide "best alignment for developing west side." The design also includes pedestrian and bike crossings. KCCI reported that the project would cut through part of Beaver Creek Golf Course and add a bridge over the four-lane highway.

The crash history is the case for closing those streets. From 2019 through 2023, the corridor's stop-controlled intersections had 47 crashes with 20 injuries. Twenty of those crashes were at Iowa 141 and NW 121st. Timberbrooke and Timberridge had 8 crashes with 3 major injuries. Over the same period, the highway segments between intersections had 42 crashes, 13 injuries and one fatality.

Four documents, four totals

The project's price depends on which document you read, and the totals have climbed as the paperwork has moved forward:

  1. $18,063,606. The Des Moines Area MPO's approved FFY 2027–2030 Transportation Improvement Program lists the "Highway 141 / Towner Drive Interchange" at this total, with $14.1 million of it local, and the line marked "Work Not Assigned."
  2. $27,645,000. The city's June 9, 2026 presentation splits this into $22.73 million for construction, $2.16 million for preliminary engineering and studies, $1.505 million for land acquisition, and $1.25 million for construction engineering.
  3. About $30 million. That was KCCI's figure in its August 3, 2026 report.
  4. $36,000,000. That's the project cost on Johnston's application for federal fiscal year 2030 regional funding, listed in the MPO's October 15, 2026 Policy Committee presentation.

The city's own slide hints at why the totals moved. Its June figures came from a February 2026 federal BUILD grant application. The project was classified as an Environmental Assessment on May 6, 2026, which allowed preliminary design to begin, and the slide says a more detailed cost estimate will follow from that work. So the earlier numbers were estimates made before design, and the latest application is the highest of the four.

In June, most of the money was still "potential"

The funding is the bigger variable. Here is how the city's June 9, 2026 presentation laid it out:

Funding line Amount Status in June 2026
STBG $2,400,000 Secured
Carbon Reduction Program $1,133,000 Secured
City of Johnston pre-design agreement $1,205,000 Secured
Iowa DOT pre-design agreement $3,200,000 Secured
BUILD grant $15,492,000 Application submitted
Community Project Funding $2,000,000 Application submitted
RISE grant $518,000 No application made yet
Developer agreement / City / Iowa DOT $1,697,000 To be determined

Secured money came to $7,938,000, a bit under 29 percent of the $27.645 million total. The single BUILD application made up more than half the budget by itself.

Two months later, the Community Project Funding line came in. U.S. Rep. Zach Nunn announced $500,000 for the interchange on August 3, a quarter of the $2 million the city had applied for. His release said more than $12.8 million had been secured, including a local commitment of more than $6.3 million, and that more funding was being pursued through a federal transportation grant.

The next decision is in the regional pot. In October, the MPO's funding subcommittee recommended $1.5 million of Johnston's $2 million request for fiscal year 2030. It recommended $0 on a separate $1.6 million request from the MPO's excess funds and $1,133,191 in carbon-reduction funding. The Policy Committee's final vote on the fiscal year 2030 awards is scheduled for November 16.

Why the schedule says 2027 in one place and 2030 in another

The construction start depends on the funding. Nunn's August release said the project would go out to bid in fall 2026, with construction starting in 2027. KCCI's report the same day said construction was expected to start in 2028 and finish by 2030. The city's schedule graphic covers design, right-of-way acquisition, utility relocation and construction, and it runs through spring 2030. The October application asks for money in a funding year labeled FFY 2030.

Each date is somebody's forecast, made at a certain point in the funding process. The fall 2026 bid date came from a release written before most of the grant money was settled, so treat it as an estimate.

What this means if you're looking at homes near Iowa 141

Look at how a home reaches the highway in the same way you'd look at its roof or furnace. Listing photos and a weekend drive show the access as it is today. The documents above show where it's going. When a home is near Iowa 141 and NW Towner Drive, a few specific questions are worth asking:

  • Which route does the home use to reach Iowa 141? If that route uses NW Towner Drive, NW Timberridge Lane or NW Timberbrooke Lane, it's on the preferred design's closure list.
  • Is the home near land the project may need? The city budgeted $1.505 million for land acquisition, and right-of-way acquisition is its own phase on the city's schedule.
  • How would construction years affect your daily drive? The current forecasts put construction somewhere between 2027 and 2030.
  • What happens to the "developing west side"? The city's design is aligned to serve that area, and a $1.697 million developer agreement line was still listed as TBD in June.

The City of Johnston's Highway 141/Towner Drive Interchange page is the place to check for updates as preliminary design moves forward.

Quick answers

Is the Towner Drive interchange approved and funded?

The city has a preferred design, the skewed roundabout. As of its June 9, 2026 presentation, $7.938 million of the $27.645 million total was secured and the rest was listed as potential funding. Since then, $500,000 in Community Project Funding was announced in August, and the MPO votes on its fiscal year 2030 awards on November 16.

Can I still get onto Iowa 141 from Towner Drive?

Not from the west side. The west leg has been closed since October 13, 2025, and the Iowa DOT directs drivers to NW 121st Street.

Will other Iowa 141 intersections in Johnston change?

Mayor Dierenfeld told KCCI that the Iowa DOT will not allow more at-grade intersections on the corridor and that the existing ones will change over time.

Why do the cost figures disagree?

They come from different stages. The $18 million TIP line, the city's $27.645 million figure based on its February 2026 grant application, KCCI's roughly $30 million and the $36 million October application were each the working number in their own document. The city has said a more detailed estimate will come out of preliminary design.